Filters
Question type

Study Flashcards

Which of the following is not a reason for a direct materials quantity variance?


A) Malfunctioning equipment
B) Purchasing of inferior raw materials
C) Increased material cost per unit
D) Spoilage of materials

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

Standards are set for only direct labor and direct materials.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct labor costs for the current period: The following data relate to direct labor costs for the current period:   What is the direct labor time variance? A)  $ 4,500 favorable B)  $18,000 unfavorable C)  $ 3,600 favorable D)  $17,100 favorable What is the direct labor time variance?


A) $ 4,500 favorable
B) $18,000 unfavorable
C) $ 3,600 favorable
D) $17,100 favorable

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows: The standard factory overhead rate is $10 per direct labor hour ($8 for variable factory overhead and $2 for fixed factory overhead)  based on 100% capacity of 30,000 direct labor hours. The standard cost and the actual cost of factory overhead for the production of 5,000 units during May were as follows:   What is the amount of the factory overhead controllable variance? A)  $10,000 favorable B)  $2,500 unfavorable C)  $10,000 unfavorable D)  $2,500 favorable What is the amount of the factory overhead controllable variance?


A) $10,000 favorable
B) $2,500 unfavorable
C) $10,000 unfavorable
D) $2,500 favorable

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

The most effective means of presenting standard factory overhead cost variance data is through a factory overhead cost variance report.

A) True
B) False

Correct Answer

verifed

verified

If the standard to produce a given amount of product is 1,000 units of direct materials at $11 and the actual was 800 units at $12, the direct materials quantity variance was $2,200 unfavorable.

A) True
B) False

Correct Answer

verifed

verified

The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows:   The amount of the factory overhead controllable variance is: A)  $2,000 unfavorable B)  $3,000 favorable C)  $0 D)  $3,000 unfavorable The amount of the factory overhead controllable variance is:


A) $2,000 unfavorable
B) $3,000 favorable
C) $0
D) $3,000 unfavorable

E) All of the above
F) B) and C)

Correct Answer

verifed

verified

  Calculate the Total Direct Materials cost variance using the above information: A)  $9,262.50 Unfavorable B)  $9,262.50 Favorable C)  $3,780.00 Unfavorable D)  $3,562.50 Favorable Calculate the Total Direct Materials cost variance using the above information:


A) $9,262.50 Unfavorable
B) $9,262.50 Favorable
C) $3,780.00 Unfavorable
D) $3,562.50 Favorable

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Standards are designed to evaluate price and quantity variances separately.

A) True
B) False

Correct Answer

verifed

verified

The principle of exceptions allows managers to


A) focus on correcting variances between standard costs and actual costs.
B) focus on correcting variances between variable costs and actual costs.
C) focus on correcting variances between competitor's costs and actual costs.
D) focus on correcting variances between competitor's costs and standard costs.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The fact that workers are unable to meet a properly determined direct labor standard is sufficient cause to change the standard.

A) True
B) False

Correct Answer

verifed

verified

The following data relate to direct materials costs for November: The following data relate to direct materials costs for November:   What is the direct materials quantity variance? A)  $3,600 favorable B)  $1,240 favorable C)  $3,600 favorable. D)  $1,240 unfavorable. What is the direct materials quantity variance?


A) $3,600 favorable
B) $1,240 favorable
C) $3,600 favorable.
D) $1,240 unfavorable.

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

Rosser Company produces a container that requires 4 yds. of material per unit. The standard price of one yard of material is $4.50. During the month, 9,500 chairs were manufactured, using 37,300 yards. Required: Journalize the entry to record the standard direct materials used in production.

Correct Answer

verifed

verified

If the actual quantity of direct materials used in producing a commodity differs from the standard quantity, the variance is termed a:


A) controllable variance
B) price variance
C) quantity variance
D) rate variance

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

The unfavorable volume variance may be due to all of the following factors except:


A) failure to maintain an even flow of work
B) machine breakdowns
C) unexpected increases in the cost of utilities
D) failure to obtain enough sales orders

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

  Calculate the total factory overhead cost variance using the above information: A)  $4,866.75 Unfavorable B)  $4,866.75 Favorable C)  $8,981.75 Favorable D)  $8,981.75 Unfavorable Calculate the total factory overhead cost variance using the above information:


A) $4,866.75 Unfavorable
B) $4,866.75 Favorable
C) $8,981.75 Favorable
D) $8,981.75 Unfavorable

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

The difference between the standard cost of a product and its actual cost is called a variance.

A) True
B) False

Correct Answer

verifed

verified

The following data is given for the Zoyza Company: The following data is given for the Zoyza Company:   Overhead is applied on standard labor hours. The factory overhead volume variance is: A)  $73,250U B)  $73,250F C)  $59,400F D)  $59,400U Overhead is applied on standard labor hours. The factory overhead volume variance is:


A) $73,250U
B) $73,250F
C) $59,400F
D) $59,400U

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Periodic comparisons between planned objectives and actual performance are reported in:


A) zero-base reports
B) budget performance reports
C) master budgets
D) budgets

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows: The standard costs and actual costs for direct materials, direct labor, and factory overhead for the manufacture of 2,500 units of product are as follows:   The amount of the direct labor time variance is: A)  $1,180 favorable B)  $1,140 unfavorable C)  $1,180 unfavorable D)  $1,140 favorable The amount of the direct labor time variance is:


A) $1,180 favorable
B) $1,140 unfavorable
C) $1,180 unfavorable
D) $1,140 favorable

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Showing 41 - 60 of 161

Related Exams

Show Answer